16 Irvine St / Selections
Prepared for Mastacon · 43 sections
Questions
00c

On site: build progress

Photographs from the site, newest first. These are real photographs, from Mastacon, not renders.

Where these come from. Mastacon's photos, sent by Stefan Mazzeo on 16 October 2026 at Franci's request (the concrete slabs; the footings with their reinforcement; the underfloor services). Captions are ours, from what the photographs show; they are not an inspection or a certification.

Slab · Mastacon photo · 1 of 3The slabs are down (photos sent 16 Oct 2026). All three dwellings' slabs, looking from the street end towards the rear, with the plumbing coming up through the slab and the garage and porch set-downs at the front
Slab · Mastacon photo · 2 of 3The slabs from the other side of the site, the stepped front edge along the street
Slab · Mastacon photo · 3 of 3The front of the slabs, with the services left ready at the porch and garage
Footings · Mastacon photo · 1 of 4Before the pour: the footing beams and slab reinforcement laid out over the pods and membrane, with the plumbing and drainage stubs standing up through it
Footings · Mastacon photo · 2 of 4The reinforcement ready, with the concrete pump at the street
Services · Mastacon photo · 3 of 4Underfloor services: pipes lagged in grey foam where they pass through the footing beams, and the plumbing risers sealed through the membrane
Services · Mastacon photo · 4 of 4Close up: a lagged pipe through a beam, under the reinforcement mesh, the bars tied and sitting on chairs above the membrane